Location Nashville , TN
Owner Uptown Property Holdings
Architect Gresham Smith
Building Size 1.24 million SF
BELL, in association with Clark Construction, is serving as the Construction Manager at Risk for the Nashville Yards Parcel 4 Office Tower. When completed, it will include 550,000 square feet of office space with 690,000 square feet of parking. The project is utilizing a fast-track schedule to meet the owner’s required completion date. The project team collaborated closely with the design team and owner to start construction less than three months after design commenced – a full eight months before the design was completed. The team is on track to deliver the building 28 months after design started.